Ten years ago this month, the review that planned this network was published. In the time it then took Greater Cambridge to appoint the consultants who would design its routes, Copenhagen's equivalent partnership of councils built a finished cycle route connecting one of its towns to the capital. A decade on, Greater Cambridge has finished one route of twelve.

Finish the Greenways

Corridor 11 of 12

Comberton Greenway

The programme's flagship — England's first cycle street at one end, and the biggest surviving new off-road route at the other.

Under construction

Map from the 2016 review showing the proposed Comberton Greenway and its links
The corridor as drawn in 2016. Reproduced from the review commissioned by Cambridgeshire County Council; base mapping © OpenStreetMap contributors. See the full document →

What became of the 8 proposals for this corridor

Built and open · 1 In design or planning · 5 Delivered differently · 1 Not in current programme · 1

What the 2016 review asked for

  • Widen the Coton to M11 bridge path, 400 m, and repair the bridge surface
  • New ramps and path from the M11 bridge into West Cambridge, 300 m
  • Replace the Bin Brook bridge on Burrell's Walk
  • A safe crossing of Long Road, assumed to be a new underpass
  • New path on field edges and bridleway, Coton via Hardwick to Comberton Village College, 5 km

What happened

  • Spring 2019Initial consultation.
  • 25 June 2020Board approves the route at £9m.
  • July 2022Camcycle consultation guide; Long Road is to get a parallel crossing, not an underpass.
  • December 2022Executive Board approval to proceed.
  • 29 September 2025Construction starts in Coton village.
  • 13 October 2025Adams Road works begin — England's first Cycle Street, carrying around 3,000 cyclists a day.
  • 5 March 2026Full business case approved, together with the Sidgwick Avenue experimental traffic order.
  • 2026Planning application submitted for the full route, Comberton to central Cambridge.
  • August 2026Adams Road complete.
  • Early 2026Coton village complete, with a 20mph limit following later in the year.

Where it stands, September 2026

Part open, part in planning. The Cambridge end — Adams Road, Grange Road, Coton village — is finished. The rural 5 km from Coton through Hardwick to Comberton Village College, the largest new off-road route left in the whole programme, is in the planning application. The review's assumed grade-separated Long Road crossing has become a surface parallel crossing; the review had argued that at peak times 'a safe crossing is important' and that a concrete box could be installed relatively quickly.

2026/27 budget £400kApproved 2020 at £9mOpen Adams Rd, Coton
Audit

Every proposal on this route

Proposed intervention (2016)Type ScaleStatus 2026What happened
Widen and upgrade the path and ramps from the edge of Coton to the M11 bridge Upgrade 400 m In design or planning In the planning application submitted in 2026.
Repair the surface of the bridge over the M11 Upgrade 1 bridge In design or planning In the scheme.
New ramps and path from the M11 bridge into the West Cambridge site at Charles Babbage Road New route 300 m In design or planning In the scheme — the link the review called it 'surprising' to have gone without.
Remove the low wall at the Adams Road / Wilberforce Road junction Upgrade Built and open Adams Road, England's first cycle street, was completed in August 2026.
Replace the Bin Brook bridge on Burrell's Walk with a wider one New structure new bridge In design or planning Still in the scheme, unbuilt.
Safe crossing of Long Road between Coton and Comberton — assumed to be a new underpass New structure underpass Delivered differently The 2016 report assumed a grade-separated crossing, noting a concrete box could be installed quickly. The scheme now proposes a surface parallel crossing.
New path on field edges and bridleway from Coton via Hardwick to Comberton Village College New route 5 km In design or planning The largest surviving new off-road route in the programme; included in the 2026 planning application.
Investigate extending the route to Cambourne, the Eversdens, Barton and Bourn New route various Not in current programme Not progressed.