Corridor 4 of 12
Bottisham Greenway
Absorbed the shared Cambridge-end section from the Swaffhams, gained Riverside, lost its underpass and its Wilbraham link.
In design or planning
What became of the 4 proposals for this corridor
What the 2016 review asked for
- Minor improvements and solar studs on the existing Stow-cum-Quy to Bottisham path
- New 1.2 km path in the A1303 verge to link with Wilbraham Road
- Upgrade the Newmarket Road Park & Ride and Ditton Lane / Fison Road junction
What happened
- Autumn 2019Initial route consultation.
- June 2020Board approval alongside Swaffhams.
- Spring 2023Updated plans presented; the route is extended west towards Cutter Ferry Bridge.
- 2023A Ditton Lane underpass is investigated and abandoned — utilities, flood risk and land acquisition cost make it 'poor value for money'. Signalised surface crossings are substituted.
- June 2023Board approval following design refinements.
- December 2025Land procurement, designs and road safety audits under way.
- 2 June – 13 July 2026Consultation on the Riverside section: wider footways, crossings, seating and cycle parking over 2.5 miles from Elizabeth Way Bridge to Stourbridge Common.
- Late 2026Construction expected to begin, subject to planning.
Where it stands, September 2026
In design with a planning application for the whole route pending, and the largest single jump in the 2026/27 budget — from £1.0m to £4.16m — implying construction is genuinely imminent. The Wilbraham Road verge path, which the review itself flagged as the weaker case, is gone.
Every proposal on this route
| Proposed intervention (2016) | Type | Scale | Status 2026 | What happened |
|---|---|---|---|---|
| Minor improvements and solar studs on the existing Stow-cum-Quy to Bottisham path | Upgrade | ~5 km | In design or planning | Carried into the scheme; designs in final review, planning application pending. |
| New path in the A1303 verge to link with Wilbraham Road | New route | 1.2 km | Not in current programme | Identified in 2016 as a weaker case; not in the current scheme. |
| Grade-separated crossing of Ditton Lane | New structure | underpass | Delivered differently | An underpass was considered and abandoned — utilities, flood risk and land cost made it 'poor value for money'. Replaced by improved signalised surface crossings. |
| Riverside, Cambridge — wider footways, crossings, seating, cycle parking | Upgrade | 2.5 miles | In design or planning | Added to the scheme after 2016; public consultation ran 2 June to 13 July 2026. |